Accessibility Tools

Water Reservoir Project

Project Timeline

August 2024
The Town of Middleton ordered a new water storage tank and dome roof through Roscoe (Prime Contractor) Construction and Aquastore. These types of tanks are not available for purchase in Canada.

Spring-Summer 2025
The Town of Middleton worked with federal departments to address cross-border import requirements related to the tank and dome roof.

August 8, 2025
The water storage tank was finally able to be transported across the border and delivered. This was followed by the dome roof three weeks later.

September 2025
The Town continued to follow up with federal authorities regarding  import and administrative matters.

October 17, 2025
The Town is advised that the products appear to be eligible under the applicable federal framework for taxation expemptions, with next steps shifting to a different federal process.

April 8, 2026
The reservoir tank is currently being filled and is nearing completition.